Rzeszów–Khmelnytskyi powerline

Rzeszów–Khmelnytskyi powerline
Location
Country Poland, Ukraine
General direction west–east
From Widełka substation, Poland 50°11′49″N 21°52′19″E / 50.19694°N 21.87194°E / 50.19694; 21.87194 (Widelka Substation)
Passes through Border between Poland and Ukraine 50°6′2″N 23°17′28.2″E / 50.10056°N 23.291167°E / 50.10056; 23.291167 (Crossing of border between Poland and Ukraine)
To Khmelnitskiy Nuclear Power Plant 50°18′5.06″N 26°38′59.10″E / 50.3014056°N 26.6497500°E / 50.3014056; 26.6497500 (Khmelnitskiy Nuclear Power Plant)
Construction information
Commissioned 1985
Decommissioned 1993
Technical information
Type Overhead transmission line
Type of current AC
Total length 395 km (245 mi)
AC Voltage 750 kV
Number of circuits 1
strainer

The Rzeszów–Khmelnytskyi powerline is an electrical power transmission line between Ukraine and Poland. It is the only 750 kV-powerline in Poland and one of the few of it in the European Union of this type.

History

The decision to build this powerline was made in 1977 and it went in operation in 1985.[1] The line went out of service after Poland joined the synchronous grid of Continental Europe (UCTE).[2] However, there was a plan to re-activate this line after 2010 by constructing a back-to-back conversion station on the Polish end of the line, but this was not implemented.[3]

In 2016 Energoatom announced it was considering disconnecting unit 2 of the Khmelnitskiy Nuclear Power Plant from the Ukrainian power grid and using the powerline to connect to the Burshtyn TES energy island which operates on the European power grid, to facilitate exports to Poland and Hungary..[4]

Technical description

It has a length of 395 kilometres (245 mi), of which 281 kilometres (175 mi) in Ukraine and 114 kilometres (71 mi) in Poland.[1] It runs from Widełka substation near Rzeszów in Poland to Khmelnitskiy Nuclear Power Plant in Ukraine. It is an AC line, which has a single circuit. It can transfer a maximum power of 1300 MVA.

As guyed portal pylons are used, strainers are from special design. They consist of three free-standing lattice towers each carrying one conductor. Each strainer tower has a crossbar at which the conductor is led around the structure on a huge insulator.

The line crosses at 50°3′24″N 25°22′5″E / 50.05667°N 25.36806°E / 50.05667; 25.36806 (Crossing of 750 kV-Powerline Widelka-Khmelnitskiy Nuclear Power Plant with 750 kV-Powerline Zakhidnoukrainska-Rivne Nuclear Power Plant) the 750 kV powerline from Zakhidnoukrainska Substation to Rivne Nuclear Power Plant, which may be the only crossing of two 750 kV powerlines in Europe.

See also

References

  1. 1 2 Klukowski, Przemysław; Krysiak, Jarosław. "Budowa i eksplotacja ukladu przesylowego 750 kV" (PDF) (in Polish). Retrieved 2008-12-23.
  2. "Activity Report 2007" (PDF). The President of the Enenergy Regulatory Office in Poland. 2007-10-31: 52. Retrieved 2008-12-23.
  3. "European, CIS and Mediterranean Interconnection: State of Play 2006. 3rd SYSTINT Report" (PDF). EURELECTRIC, UCTE. January 2007: 52. 2007-030-0428. Retrieved 2010-11-10.
  4. Alexander Bor (27 May 2016). "Ukraine to build power line for power exports to Poland, Hungary: EnergoAtom". Platts. Retrieved 16 June 2016.
This article is issued from Wikipedia - version of the 6/16/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.